E1: Acceptable Risk
Roel Heusschen
|
Report No.
|
WE/MoC-16-2025 |
|
Approved
|
Approved
|
|
Location/Facility
|
Bestla Development and Draugne D-1BH |
|
Date Originated
|
2025/02/12 |
|
Deadline Passed
|
2025/04/30 |
|
Not Closed
|
Should be |
Minor
in Bestla Development and Draugne D-1BH
-
Regulations & mitigating measures (0)
Risk Assessment Conducted
Risk Assessment conducted in MOC form attached
Has been Approved
Compensating Measures
Assign new resource or alternatively hire qualified resource to take over the HSEQ coordinator responsibilities towards the OKEA Draugne and Bestla projects
Who needs to be notified?
Daniel Meyer; Håvard JEnsås; Gertie Nygaard
Actions
Prepare formal written handover to the new and / or temporary resource allocated to both Betsla and Draugen projects
Hire or assign qualified and experienced new HSEQ coordinator to fill the existing gap in the Bestla and Draugen project organization
Inform OKEA in writing about the change in the organization towards the Draugen and Bestla OKEA projects
OKEA organization informed formaly by email 12-02-2025. Email uploaded and attached
Complete the outsanding and critical Draugen and Bestla project delivereables such as including but not limited to
- AfC Bestla Development
- Bridging Documentation towrads Bestla Development
Verify, review and approve written handover to new HSEQ coordinator towards Draugen and Bestla
WE critical information to be contained in WE SP upon return of IT equipment
Acceptable Risk
-
Risk Assessment
Risk Not AcceptableRisk Mitigation
Must be EvaluatedAcceptable RiskE1E
- Term
- Almost certain to occur
- Industry Terms
- Incident could happen more than once during this operation
- Chance of Occurence
- 80%
- Frequency of Occurence
- Once a month
1
- Very low impact
- Negligible
- First Aid Required
-
Oil 100 litre Black 10 litre Red 1m3 Yellow 10m3 Green 100m3 - 1 day lost time - Less than 1MNOK
- Information only to authorities. No further discussion.
Probability and Impact of Event
PROBABILITY / LIKELIHOOD OF EVENT C Term In Industry Terms Percentage Chance of Occurence Frequency of Occurence A Very Unlikely to occur Never heard of in industry 5% Once in 10 years B Unlikely to occur Has occured in industry 5% - 20% Once in 5 years C Likely to occur Incident could occur in North Sea Area 20% - 50% Once in 2 years D Very likely to occur Incident could occur during our operations 50% - 80% 2 times per year E Almost certain to occur Incident could happen more than once during this operation 80% Once a month IMPACT / CONSEQUENCE OF EVENT C Term Well Control People Environmental Damage Asset Damage Reputation Damage 1 Very low impact Negligible First Aid Required Oil 100 litre
Black 10 litre
Red 1m3
Yellow 10m3
Green 100m31 day lost time
Less than 1MNOKInformation only to authorities. No further discussion. 2 Low Impact Non Classified Restricted Work Case / Medical Treatment Case Oil 100 litre
Black 10 litre
Red 1m3
Yellow 10m3
Green 100m31 day lost time
1 MNOK to 5 MNOKOperator in dialog with authorities. No mention of Wellesley. 3 Medium Impact Regular Well Control Incidents Lost Time Incident / Reportable Incident Oil 1m3
Black 100 litre
Red 10m3
Yellow 100m3
Green 1000m33 days lost time
5 MNOK to 10 MNOKOperator investigated by authorities. No mention of Wellesley. 4 High Impact Serious Well Control Incidents Likely Permanent Disability Oil 100m3
Black 1m3
Red 100m3
Yellow 1000m3
Green 10000m314 days lost time
10 MNOK to 30 MNOKLocal media coverage. Wellesley included in coverage or approached by authorities. 5 Very High Impact Critical Well Control Incidents Single or Multiple Fatalities Oil 1000m3
Black 10m3
Red 1000m3
Yellow 10000m3
Green 100000m330 days lost time
More than 30 MNOKNational coverage. Wellesley included in coverage.